PE Floating Structure

  • 01

    Bidding/Expert Consultation and Design The specialized design begins after the bidding, planning of design, and selection of the location for installation.

  • 02

    Drafting BOM and Preparing Raw and Subsidiary Materials BOM drafted and orders are placed to prepare raw and subsidiary materials

  • 03

    Government-Supplied Materials Reception Government-supplied materials are received, cut to form, and sorted

  • 04

    Floating Pipe Assembly
    (Government-Supplied Material Assembly)
    Fusion assembly between floating pipe and pipe

  • 05

    Floating Pipe Bracket Installation (Government-Supplied Material Assembly) Bracket assembled on floating pipe
    Assembled to fix pipe to upper deck

  • 06

    Float and Upper Deck Assembly (Government-Supplied Material Assembly) PE panels assembled onto installation areas on floating pipes and brackets

  • 07

    Cross Bollard Assembly Cross bollard assembled onto upper surface
    The part where the ship is fixed when mooring

  • 08

    Transportation and Installation Transported to installation location and pontoon bridge is installed

  • 09

    Anchor Assembly The process where the anchor is fixed to the sea floor by attaching chains and lines for the process of fixing for pontoon mooring