Bidding/Expert Consultation and Design The specialized design begins after the bidding, planning of design, and selection of the location for installation.
Drafting BOM and Preparing Raw and Subsidiary Materials BOM drafted and orders are placed to prepare raw and subsidiary materials
Government-Supplied Materials Reception Government-supplied materials are received, cut to form, and sorted
Floating Pipe Assembly (Government-Supplied Material Assembly) Fusion assembly between floating pipe and pipe
Floating Pipe Bracket Installation (Government-Supplied Material Assembly) Bracket assembled on floating pipe Assembled to fix pipe to upper deck
Float and Upper Deck Assembly (Government-Supplied Material Assembly) PE panels assembled onto installation areas on floating pipes and brackets
Cross Bollard Assembly Cross bollard assembled onto upper surface The part where the ship is fixed when mooring
Transportation and Installation Transported to installation location and pontoon bridge is installed
Anchor Assembly The process where the anchor is fixed to the sea floor by attaching chains and lines for the process of fixing for pontoon mooring